153 MW capacity
Agoyan, Provincia Tungurahua; Cantón Baños de Agua Santa; Sistema hidrográfico Pastaza; Río Pastaza, Ecuador
Status: In Operation
380 hectares flooded
2 hectares per MW
Subtropical humid forest
-52 million USD
net present value
Be the first to start a conversation by posting a comment
Analysis table
Results
Net Present Value:
-52.0 million USD
Hectares flooded per MW:
2 hectares per MW
CO₂ emissions:
48,640 metric tonnes
CO₂ emissions per MW:
318 metric tonnes per MW
People displaced per megawatt:
0 people per MW Inputs and assumptions
Installed capacity :
153 MW
Capacity used:
90%
Area flooded:
380 hectares
Vegetation type:
Subtropical humid forest
People displaced:
0 people displaced
Construction time:
4 years
Construction cost:
190,030,000 USD
Transmission infrastructure cost:
0 USD
Wholesale price of energy:
26.2 USD
Economic discount rate:
12.6%
Submitted by Juan Carlos Rivera on 26 August 2009 - 10:29pm
Other analyses of the Agoyan project
No other analyses of this project. Sign in or register now to create a new analysis.
HydroCalculator Tool Help
CSF e-newsletter
I want to know the latest conservation news, and hear about upcoming CSF projects and courses.
Upcoming CSF Courses
CSF offers training in economic tools to empower local conservation organizations, decision-makers, and communities.
Economic Tools for Conservation - 2010 International Course
Monday, 9 August, 2010 - Friday, 20 August, 2010
Thursday, 15 April 2010
0 people displaced
0 people per MW