HydroCalculator

Ferreira Gomes, Ferreira Gomes, Amapá, Brazil

River: Araguari

Status: Under construction

4 hectares per MW

2 people per MW

Enable javascript to view charts.

Results

Net Present Value-404,326 thousand BRL
NPV including net greenhouse gas emissions-408,287 thousand BRL
Internal Rate of Return5.17%
Hectares flooded per MW4 hectares per MW
Gross CO₂ equivalent emissions7,102 thousand metric tonnes
Gross CO₂ equivalent per MW28,183 metric tonnes per MW
Hectares flooded per MW4 hectares per MW
People displaced per megawatt2 people per MW

Inputs and assumptions

People displaced400 people displaced
Area flooded1,122 hectares
Installed capacity 252 MW
Capacity used59%
Construction time3 years
Construction cost910,000,000 BRL
Transmission infrastructure cost0 BRL
Wholesale price of energy69.82 BRL
Economic discount rate10.5%