2 thousand MW capacity
Inambari 5%, Chiforongo, Peru
River: Inambari
Status: Proposed project
38 thousand hectares flooded
17 hectares per MW
Tropical rain forest
3 thousand people displaced
1 person per MW
1,203 million PEN
net present value
(Excluding environmental costs)
Javascript is required to view this map.
Analysis table
Results
Net Present Value:
1,203 million PEN
NPV including net greenhouse gas emissions:
873,106 thousand PEN
Internal Rate of Return:
11.2%
Hectares flooded per MW:
17 hectares per MW
Gross CO₂ equivalent emissions:
230,727 thousand metric tonnes
Gross CO₂ equivalent per MW:
104,876 metric tonnes per MW
People displaced per megawatt:
1 person per MW Inputs and assumptions
Installed capacity :
2,200 MW
Capacity used:
60%
Area flooded:
37,800 hectares
Vegetation type:
Tropical rain forest
People displaced:
3,261 people displaced
Construction time:
5 years
Construction cost:
10,000,000,000 PEN
Transmission infrastructure cost:
0 PEN
Wholesale price of energy:
157 PEN
Economic discount rate:
10% 16 March 2010 – 8:49pm
Other analyses of the Inambari 5% project
No other analyses of this project. Sign in or register now to create a new analysis.
HydroCalculator Tool Help
CSF e-newsletter
I want to know the latest conservation news, and hear about upcoming CSF projects and courses.
Upcoming CSF Courses
CSF offers training in economic tools to empower local conservation organizations, decision-makers, and communities.
Herramientas Económicas para la Conservación en la Amazonía Andina - Perú 2012
Monday, 28 May, 2012 - Friday, 8 June, 2012
Friday, 23 March 2012
Economic Tools for Conservation and Infrastructure Planning in the Albertine Rift
Monday, 11 June, 2012 - Friday, 22 June, 2012
Monday, 30 April 2012
Ferramentas Econômicas para a Conservação e Planejamento de Infraestrutura na Amazônia - Formulário de Inscrição
Monday, 13 August, 2012 - Friday, 24 August, 2012
Saturday, 16 June 2012
Comments
5% discount rate
Analísis del proyecto Inambari hecho con tasa de descuento e 5%.