Inambari 5%, Chiforongo, Peru

River: Inambari

Status: Proposed project

17 hectares per MW

Tropical rain forest

1 person per MW

Javascript is required to view this map.

Analysis table

Results

Net Present Value: 
1,203 million PEN
NPV including net greenhouse gas emissions: 
873,106 thousand PEN
Internal Rate of Return: 
11.2%
Hectares flooded per MW: 
17 hectares per MW
Gross CO₂ equivalent emissions: 
230,727 thousand metric tonnes
Gross CO₂ equivalent per MW: 
104,876 metric tonnes per MW
People displaced per megawatt: 
1 person per MW

Inputs and assumptions

Installed capacity : 
2,200 MW
Capacity used: 
60%
Area flooded: 
37,800 hectares
Vegetation type: 
Tropical rain forest
People displaced: 
3,261 people displaced
Construction time: 
5 years
Construction cost: 
10,000,000,000 PEN
Transmission infrastructure cost: 
0 PEN
Wholesale price of energy: 
157 PEN
Economic discount rate: 
10%

Comments

5% discount rate

Analísis del proyecto Inambari hecho con tasa de descuento e 5%.

Other analyses of the Inambari 5% project

No other analyses of this project. Sign in or register now to create a new analysis.