2 thousand MW capacity
Inambari, Mazuko, Peru
River: Inambari
Status: Proposed project
38 thousand hectares flooded
17 hectares per MW
Tropical rain forest
4 thousand people displaced
2 people per MW
3 billion PEN
net present value
(Excluding environmental costs)
Analysis table
Results
Net Present Value:
3,098 million PEN
NPV including net greenhouse gas emissions:
2,852 million PEN
Internal Rate of Return:
13.9%
Hectares flooded per MW:
17 hectares per MW
Gross CO₂ equivalent emissions:
230,727 thousand metric tonnes
Gross CO₂ equivalent per MW:
104,876 metric tonnes per MW
People displaced per megawatt:
2 people per MW Inputs and assumptions
Installed capacity :
2,200 MW
Capacity used:
71%
Area flooded:
37,800 hectares
Vegetation type:
Tropical rain forest
People displaced:
4,000 people displaced
Construction time:
5 years
Construction cost:
10,671,988,400 PEN
Transmission infrastructure cost:
883,000,000 PEN
Wholesale price of energy:
186 PEN
Economic discount rate:
11% jose serra vega
2 March 2011 – 11:32pm
Other analyses of the Inambari project
| Details | Links | Capacity (MW) | Net Present Value | CO₂ emissions (t/MW) | Inundated land (ha/MW) | Displaced people / MW |
|---|---|---|---|---|---|---|
| jfgordilloj, Inambari, Madre de Dios, Proposed project | View | 2,000 MW | 668,657 thousand PEN | 56,000 | 21 | 4 |
| Alfonso Malky, Inambari, Madre de Dios, Proposed project | View | 2,200 MW | 926,213 thousand PEN | 53,000 | 17 | 1.0 |
| John Reid, Chiforongo, Proposed project | View | 2,200 MW | -120,844 thousand PEN | 53,000 | 17 | 1 |
Sign in or register now to create a new analysis.
HydroCalculator Tool Help
CSF e-newsletter
I want to know the latest conservation news, and hear about upcoming CSF projects and courses.
Upcoming CSF Courses
CSF offers training in economic tools to empower local conservation organizations, decision-makers, and communities.
Herramientas Económicas para la Conservación en la Amazonía Andina - Perú 2012
Monday, 28 May, 2012 - Friday, 8 June, 2012
Friday, 23 March 2012
Economic Tools for Conservation and Infrastructure Planning in the Albertine Rift
Monday, 11 June, 2012 - Friday, 22 June, 2012
Monday, 30 April 2012
Ferramentas Econômicas para a Conservação e Planejamento de Infraestrutura na Amazônia - Formulário de Inscrição
Monday, 13 August, 2012 - Friday, 24 August, 2012
Friday, 1 June 2012
Comments
Comparar
Si quieres comparar con el análisis que yo hice vea al final de la página de resultados.
Algunos Cambios
He cambiado el costo de la construcción para 10671988400 PEN a 3964300000 PEN y el precio al por mayor de energía a partir de 99 soles a 165 soles, para reflejar los costos más precisos.
Un Cambio Mas
Después de una investigación aún más, he cambiado el precio de la energía de 165 a 186 soles.