Inambari o, Masuco, Peru

River: inambari

Status: Proposed project

19 hectares per MW

Mix of crops & tropical rainforest (50/50)

2 people per MW

Be the first to start a conversation by posting a comment

Add a comment


Analysis table

Results

Net Present Value: 
-4,244 million PEN
NPV including net greenhouse gas emissions: 
-4,240 million PEN
Internal Rate of Return: 
5.92%
Hectares flooded per MW: 
19 hectares per MW
Gross CO₂ equivalent emissions: 
115,961 thousand metric tonnes
Gross CO₂ equivalent per MW: 
57,981 metric tonnes per MW
People displaced per megawatt: 
2 people per MW

Inputs and assumptions

Installed capacity : 
2,000 MW
Capacity used: 
70%
Area flooded: 
37,800 hectares
Vegetation type: 
Mix of crops & tropical rainforest (50/50)
People displaced: 
4,000 people displaced
Construction time: 
5 years
Construction cost: 
10,000,000,000 PEN
Transmission infrastructure cost: 
800,000,000 PEN
Wholesale price of energy: 
96 PEN
Economic discount rate: 
11%