Peninsula, Provincia Tungurahua; Cantón Ambato;Sistema Hidrográfico Pastaza;Río Ambato, Ecuador

Status: In Operation

0 hectares per MW

Mountain (montane) forest

0 people per MW

Be the first to start a conversation by posting a comment

Add a comment


Analysis table

Results

Net Present Value: 
-2.9 million USD
Hectares flooded per MW: 
0 hectares per MW
CO₂ emissions: 
87 metric tonnes
CO₂ emissions per MW: 
29 metric tonnes per MW
People displaced per megawatt: 
0 people per MW

Inputs and assumptions

Installed capacity : 
3 MW
Capacity used: 
90%
Area flooded: 
1 hectare
Vegetation type: 
Mountain (montane) forest
People displaced: 
0 people displaced
Construction time: 
2 years
Construction cost: 
6,920,000 USD
Transmission infrastructure cost: 
0 USD
Wholesale price of energy: 
38.5 USD
Economic discount rate: 
12.6%

Other analyses of the Peninsula project

No other analyses of this project. Sign in or register now to create a new analysis.