9 thousand MW capacity
Rene proy, Itaituba, Bolivia
River: Tapajós
Status: Proposed project
20 thousand hectares flooded
2 hectares per MW
Tropical moist deciduous forest
-18 billion USD
net present value
(Excluding environmental costs)
Be the first to start a conversation by posting a comment
Analysis table
Results
Net Present Value:
-17,651 million USD
NPV including net greenhouse gas emissions:
-17,381 million USD
Internal Rate of Return:
0.860%
Hectares flooded per MW:
2 hectares per MW
Gross CO₂ equivalent emissions:
77,941 thousand metric tonnes
Gross CO₂ equivalent per MW:
8,959 metric tonnes per MW
People displaced per megawatt:
0 people per MW Inputs and assumptions
Installed capacity :
8,700 MW
Capacity used:
60%
Area flooded:
20,000 hectares
Vegetation type:
Tropical moist deciduous forest
People displaced:
1,400 people displaced
Construction time:
7 years
Construction cost:
25,000,000,000 USD
Transmission infrastructure cost:
3,980,000,000 USD
Wholesale price of energy:
40 USD
Economic discount rate:
12.8% Rene
12 September 2011 – 9:42pm
Other analyses of the Rene proy project
No other analyses of this project. Sign in or register now to create a new analysis.
HydroCalculator Tool Help
CSF e-newsletter
I want to know the latest conservation news, and hear about upcoming CSF projects and courses.
Upcoming CSF Courses
CSF offers training in economic tools to empower local conservation organizations, decision-makers, and communities.
Herramientas Económicas para la Conservación en la Amazonía Andina - Perú 2012
Monday, 28 May, 2012 - Friday, 8 June, 2012
Friday, 23 March 2012
Economic Tools for Conservation and Infrastructure Planning in the Albertine Rift
Monday, 11 June, 2012 - Friday, 22 June, 2012
Monday, 30 April 2012
Ferramentas Econômicas para a Conservação e Planejamento de Infraestrutura na Amazônia - Formulário de Inscrição
Monday, 13 August, 2012 - Friday, 24 August, 2012
Friday, 1 June 2012
1,400 people displaced
0 people per MW