São Luiz do Tapajós, Itaituba, Pará, Brazil

River: Tapajós

Status: Proposed project

13 hectares per MW

0 people per MW

Enable javascript to view charts.

Results

Net Present Value-5,041 million BRL
NPV including net greenhouse gas emissions-5,552 million BRL
Internal Rate of Return3.11%
Hectares flooded per MW13 hectares per MW
Gross CO₂ equivalent emissions479,040 thousand metric tonnes
Gross CO₂ equivalent per MW78,045 metric tonnes per MW
Hectares flooded per MW13 hectares per MW
People displaced per megawatt0 people per MW

Inputs and assumptions

People displaced977 people displaced
Area flooded78,481 hectares
Installed capacity 6,138 MW
Capacity used60%
Construction time5 years
Construction cost9,200,000,000 BRL
Transmission infrastructure cost0 BRL
Wholesale price of energy24 BRL
Economic discount rate10.5%

Comments

A capacidade utilizada foi estimada em 60%, não existe esta informação disponível.

O leilão deste empreendimento acontecera entre os anos de 2012 e 2013.

O preço da energia: foi realizada uma média do preço de venda de energia ao distribuidor no ano de 2011. O preço da energia só pode ser afirmado após o resultado do leilão, que leva em conta aquela empresa que da o menor lance no valor do preço da energia.

Post new comment

  • Web page addresses and e-mail addresses turn into links automatically.
  • Allowed HTML tags: <a> <em> <strong> <cite> <code> <pre> <ul> <ol> <li> <dl> <dt> <dd> <span> <blockquote> <div> <img> <del> <ins> <h2> <h3>
  • Lines and paragraphs break automatically.

More information about formatting options

Type the characters you see in this picture. (verify using audio)
Type the characters you see in the picture above; if you can't read them, submit the form and a new image will be generated. Not case sensitive.