Sibimbe, Provincia Bolívar/Los Ríos; Cantón Echeandía; Sistema hidrográfico Guayas; Río Sibimbe, Ecuador

Status: In Operation

0 hectares per MW

Subtropical humid forest

0 people per MW


Analysis table

Results

Net Present Value: 
26.2 million USD
Hectares flooded per MW: 
0 hectares per MW
CO₂ emissions: 
128 metric tonnes
CO₂ emissions per MW: 
9 metric tonnes per MW
People displaced per megawatt: 
0 people per MW

Inputs and assumptions

Installed capacity : 
15 MW
Capacity used: 
90%
Area flooded: 
1 hectare
Vegetation type: 
Subtropical humid forest
People displaced: 
0 people displaced
Construction time: 
2 years
Construction cost: 
19,860,000 USD
Transmission infrastructure cost: 
0 USD
Wholesale price of energy: 
96.7 USD
Economic discount rate: 
16.5%

Other analyses of the Sibimbe project