Tigreurco, Provincia Bolívar; Cantón Guaranda; Sistema hidrográfico Guayas, Río Payagua, Ecuador

Status: Proposed project

0 hectares per MW

Tropical rain forest

0 people per MW

Be the first to start a conversation by posting a comment

Add a comment


Analysis table

Results

Net Present Value: 
571,929 USD
Hectares flooded per MW: 
0 hectares per MW
Gross CO₂ equivalent emissions: 
193 metric tonnes
Gross CO₂ equivalent per MW: 
69 metric tonnes per MW
People displaced per megawatt: 
0 people per MW

Inputs and assumptions

Installed capacity : 
2.8 MW
Capacity used: 
90%
Area flooded: 
1 hectare
Vegetation type: 
Tropical rain forest
People displaced: 
0 people displaced
Construction time: 
1 year
Construction cost: 
4,070,000 USD
Transmission infrastructure cost: 
0 USD
Wholesale price of energy: 
46.9 USD
Economic discount rate: 
15.2%

Other analyses of the Tigreurco project

No other analyses of this project. Sign in or register now to create a new analysis.