Results

Net Present Value-992,749 million BRL
NPV including net greenhouse gas emissions-992,712 million BRL
Hectares flooded per MW8 hectares per MW
Gross CO₂ equivalent emissions84,761 thousand metric tonnes
Gross CO₂ equivalent per MW19,967 metric tonnes per MW
Hectares flooded per MW8 hectares per MW
People displaced per megawatt0 people per MW

Inputs and assumptions

People displaced0 people displaced
Area flooded32,000 hectares
Installed capacity 4,245 MW
Capacity used100%
Construction time7 years
Construction cost5,054,617,000 BRL
Transmission infrastructure cost1,374,690,895,830 BRL
Wholesale price of energy100 BRL
Economic discount rate10%